Warning: Illegal string offset 'singular_post_taxonomy' in /home/customer/www/calhsr.com/public_html/wp-content/themes/canvas/functions/admin-functions.php on line 2952

Land purchases for initial construction way behind schedule

The contract signed with the design- build construction team led by Tutor Perini in August had a detailed list of properties that the CHSRA would have to buy and the date each parcel would be available to the contractor.

The most recent report  on January 16th notes that there are significant delays.How far behind is the Authority from the schedule included with the August 2013 contract?Very far.

row

 

Comments are closed.