Land purchases for initial construction way behind schedule

The contract signed with the design- build construction team led by Tutor Perini in August had a detailed list of properties that the CHSRA would have to buy and the date each parcel would be available to the contractor. The most recent report  on January 16th notes that there are significant delays.How far behind is […]